Portalfräsen Upgrade Project 2025 and 2026

Project history for the Portalfräsen rebuild: stronger frame, JMC servos, new electronics, and a new table with replaceable plastic strips and T-tracks. The machine is not yet back in service.

Portalfräsen with table, gantry and wall-mounted dust collection, Oct 2026

Portalfräsen with table, gantry and wall-mounted dust collection, Oct 2026


13 October 2026. Earlier overview

Before and after


Before

After (result or target)

Work area

835 × 885 mm, ~140 mm Z

Target ~900 × 1000 × 200 mm; 1024 mm Y travel measured Jul 2026

X/Y speed

4000 mm/min

9600 mm/min motion (May 2026) — not a cutting feed

Acceleration

–

Target > 2000 mm/s²

Frame

Aluminium gantry

Heavier extrusions + ~200 kg laser-cut steel reinforcement

Drives

Unknown

JMC servos (660 W design)

Table

MDF spoilboard with wood screws

Fixed plastic base, replaceable 25 mm strips, aluminium T-tracks, 20 mm bench-dog holes (in progress)

Accuracy

~0.1 mm (old spec)

Not yet measured

Spindle / VFD

2.2 kW water-cooled, BD600 (since Jan 2025)

Kept

Control

LinuxCNC, Mesa 7i76E

Same, with rebuilt cabinets and config

Dust

DC2500, curtain, dust shoe

Collectors, cyclone, curtain and hoses reinstalled (Oct 2026); new dust shoe pending

MQL

–

Dynacut MDE, plumbed Jul 2026

Timeline

2025

  • Mar: rebuild plan — new extrusions and laser-cut steel, JMC servos, plastic table with T-tracks.

  • Mar–Apr: steel parts delivered.

  • Aug: volunteer kickoff (13 Aug) with work groups for mechanics, electronics, software, table, dust, welding, coating and documentation. Old extrusions turned out to be 45 × 90 (not 40 × 80) — new profiles ordered. Parts powder coated.

  • Sep–Dec: frame assembly. Y servos mounted 28 Dec; frame corners with six screws and an extra bracket each.




Rebuild CAD render

Rebuild CAD render


Steel plates delivered

Steel plates delivered


Frame assembly, Sep 2025

Frame assembly, Sep 2025


2026

  • Jan: powder-coated portal side plates mounted; grease lines rerouted.

  • Feb: curtain carrier installed.

  • Feb–Mar: power and Mesa cabinets rebuilt.

  • Apr–May: VFD cabinet got an interference filter and three-phase input.

  • May: LinuxCNC installed (24 May); motion working at 9600 mm/min (31 May).

  • Jun: first chips in wood (7 Jun). Encoder realigned, gantry squared on the Y home switches, Z recalibrated (2.5 mm pitch).

  • Jul: wood/aluminium base table mounted. Z drive changed to S3M belts. Air and MQL plumbing connected.

  • Aug: plastic table top mounted.

  • Sep: T-tracks and strips installed (20 Sep). Material stops and bench-dog clamps delivered.

  • Oct: servo tuning (4 Oct). Dust collectors, curtain and hoses installed (10–11 Oct). Clamping-bar holes machined (11 Oct); front T-track clearance can't be reached with current Y travel.




Y servo installation

Y servo installation


Portal side plates

Portal side plates


Mesa cabinet

Mesa cabinet


T-tracks and strips

T-tracks and strips


Clamping-bar holes

Clamping-bar holes


Dust collectors

Dust collectors


Strip curtain installed

Strip curtain installed


Electronics cabinets

Photographed on 13 October 2026. Original photo album.

Mesa 7i76E control cabinet

Spindle VFD cabinet

Mesa 7i76E control cabinet, 13 October 2026

Mesa 7i76E control cabinet, 13 October 2026


Spindle VFD cabinet, 13 October 2026

Spindle VFD cabinet, 13 October 2026


Power cabinet overview

Power cabinet detail

Power cabinet overview with door-mounted controls, 13 October 2026

Power cabinet overview with door-mounted controls, 13 October 2026


Power cabinet interior detail, 13 October 2026

Power cabinet interior detail, 13 October 2026


Table notes

  • Plastic strips are replaceable and can be resurfaced, but the M8 fixing heads limit how thin they can go.

  • T-tracks for clamps; 20 mm bench-dog holes for stops.

MQL notes

The MQL produces an oil aerosol (15–35 µm droplets, manual p. 7). Disconnect air and power and depressurise before refilling (pp. 5, 12). Adjustment: p. 14.

Remaining work

  • Table features, front T-track clearance, surfacing; confirm final travel.

  • Dust shoe, side panels, motor dust covers, guide wipers.

  • Save servo settings (they didn't persist after power cycle in Sep); check geometry and accuracy.

  • Software emergency stop; spindle enable/direction.

  • Tool setter and pendant.

  • MQL test while cutting.

  • Operating procedure and access rules.