Betongsuggan Commissioning Project 2025 and 2026

Project history for Betongsuggan. The machine was bought as an unfinished concrete-frame CNC mill (~90% complete) and commissioned in 2025–2026. For current use, see the main page.

Betongsuggan with enclosure and printed covers

Betongsuggan with enclosure and printed covers


August 2026.

Before and after


Bought

Now

Stand

Too wide for the doors

Narrowed ~20 cm, wheels and feet, rubber supports

Axes

Servos, rails, ballscrews (partly removed for transport)

Reassembled; all axes running since Oct 2025

Spindle

Seller kept the ATC spindle

3.7 kW, 800 Hz, ER20, water-cooled; no tool changer

Electrics

Mesa 7i76E, Delta servo drives, VFD; messy wiring

Rebuilt cabinet, front controls, emergency stop

Lubrication

Central oil present but stuck

Central oil working; Dynacut MDE MQL for the tool

Enclosure

None

Aluminium frame, composite panels, polycarbonate doors, PETG covers

Workholding

Steel table, few fixing points

Small vise; better hole pattern proposed

Chips

No drawer

Still no drawer

Timeline

2025

  • Mar: stand cut and welded ~20 cm narrower; table, X motor and Z plate removed to save weight. Replacement spindle ordered and delivered. CAD corrected against a 3D scan (errors from cm to mm).

  • May: moved into the basement.

  • Aug: wheels and feet on the base. Work moved to #metal-cnc.

  • Sep: rubber supports fitted; moved into place with ~1 mm doorway clearance. Base plate and rubber cover belt refitted.

  • Oct: homing fixed (limit switches needed power); all axes moving.

  • Nov: spindle installed.




Lifted off the original stand

Lifted off the original stand


Cutting the stand

Cutting the stand


Stand in two halves

Stand in two halves


CAD of the narrowed stand

CAD of the narrowed stand


Base plate attached, Sep 2025

Base plate attached, Sep 2025


Back on the narrowed stand, Nov 2025

Back on the narrowed stand, Nov 2025


Spindle installed, Nov 2025

Spindle installed, Nov 2025


2026

  • Jan: spindle water cooling working. Central oil distributors freed (dried oil). Electrical system drawn in QElectroTech.

  • Feb: first plastic parts (PE, then Delrin). Delayed-stop controller ordered. LinuxCNC with QtDragon HD tested on new Dell P2424HT touchscreens.

  • Mar: emergency stop working.

  • Apr: rewiring and reassembly. 23 Apr: VFD smoked after a guessed brake-resistor connection to P+/P−; movement restored 28 Apr.

  • Jul: composite enclosure panels mounted.

  • Aug: polycarbonate doors finished (5 Aug); MQL installed and tested; ~1.6 kg of PETG covers printed and fitted (18 Aug); foam strip between the doors.

First plastic test piece, Feb 2026

First plastic test piece, Feb 2026

Electrical rebuild, Apr 2026

Electrical rebuild, Apr 2026


Doors

Rear cover

Foam strip

MQL

Finished doors

Finished doors


PETG rear cover and cable guide

PETG rear cover and cable guide


Foam strip between doors

Foam strip between doors


MQL and front controls

MQL and front controls


MQL notes

  • Runs on 24 V with a manual switch. Flow kept low; members must not turn up the regulators.

  • The solenoids didn't close fully at first; whether that was fixed isn't recorded.

  • The MQL produces an oil aerosol (15–35 µm droplets, manual p. 7). Disconnect air and power and depressurise before refilling (pp. 5, 12).

Remaining work

  • Servo tuning (possible overshoot).

  • Axis accuracy test; recalibrate the servo drives if needed.

  • Maximum speeds and accelerations in LinuxCNC.

  • Spindle speed calibration and reverse.

  • VFD configuration, including the brake resistor.

  • Tool-length probe.

  • Mini-PC (Topton N150) setup.

  • MQL solenoid shutoff.

  • CAM parameters.

  • Chip drawer.

  • Better workholding — proposed: offset M12 grids with 12 mm locating counterbores, possibly SMW Modvise.

  • Up-to-date electrical drawings.

  • Magnets to keep the electronics cabinet door shut.

  • Magnet or similar to stop the door wobbling while the machine moves.